FY 2022 Major Projects
Projects in Planning
Central Power Plant Steam Pressure Regulator Valve System
Edward and Rosalie Ginsberg Building
Hayward Street Geothermal Facility
Michigan Stadium Scoreboard Replacement
New North Campus Undergraduate Housing
New Building for College of Pharmacy
New Central Campus Recreation Building Replacement
Horace H. Rackham Educational Memorial 100 Farnsworth Street, Detroit Michigan
University of Michigan Health
- Brighton Center for Specialty Care Linear Accelerator Expansion
- Brighton Center for Specialty Care Shell Space Utilization for New Operating Rooms
- University Hospital Electrical Substation Replacement
Projects in Progress
Chemistry Building and Willard H. Dow Laboratory East Campus Switching Station Upgrade | Work started November 2021 with an estimated completion date of September 2023. Financing is from utilities reserves.
Dean Road Transportation Facility | Work started January 2021 with an estimated completion date of September 2022. Financing is from Logistics, Transportation, and Parking.
East University Chiller Plant Chiller Replacement | Work started December 2021 with an estimated completion date of September 2023. Financing is from utilities reserves.
Robben W. and Aldyth Fleming Administration Building Demolition | Work started May 2022 with an estimated completion date of September 2022. Financing is from reserves.
William W. Cook Legal Research Library and Hutchins Hall Exterior Repairs | Work started July 2021 with an estimated completion date of December 2022. Financing is from the general fund.
Leinweber Computer Science and Information Building | Work started May 2022 with an estimated completion date of September 2025. Financing is from state capital appropriation, the Office of the Provost, the College of Engineering and the School of Information.
Medical Science Research Buildings I, II and III Installation of Back Up Generators | Work started July 2021 with an estimated completion date of December 2022. Financing is from the Medical School.
Palmer Field Temporary Recreation Facility | Work started June 2022 with an estimated completion date of December 2022. Financing is from reserves.
President’s Residence Infrastructure Renovation | Work started May 2022 with an estimated completion date of September 2023. Financing is from reserves.
Harold T. and Vivian B. Shapiro Library Third Floor Renovation | Work started March 2022 with an estimated completion date of March 2023. Financing is from gifts and the Office of the Provost.
A. Alfred Taubman Biomedical Science Research Building Vivarium Expansion | Work started February 2021 with an estimated completion date of January 2023. Financing is from the Medical School.
University of Michigan Health | Financing is from University of Michigan Health.
- The D. Dan and Betty Kahn Healthcare Pavilion at University of Michigan Health | Work restarted May 2021 with an estimated completion date of June 2025.
- Samuel and Jean Frankel Cardiovascular Center Positron Emission Tomography/Computed Tomography Scanner Project | Work started February 2022 with an estimated completion date of December 2022.
- C.S Mott Children’s and Von Voigtlander Women’s Hospitals Emergency and Psychiatric Services Renovation | Work started March 2022 with an estimated completion date of March 2023.
- University Hospital and University Hospital South Clinical Pathology Laboratories | Work started January 2020 with an estimated completion date of December 2023.
- 7300 West Joy Road, Dexter, Michigan Specialty Pharmacy Expansion | Work started June 2022 with an estimated completion date of June 2023.
- Rogel Cancer Center Exterior Improvements | Work started July 2021 with an estimated completion date of July 2022. Financed by University of Michigan Health and the general fund.
- University Hospital Air Handling Unit Replacement | Work started December 2021 with an estimated completion date of September 2022. Financed by insurance reserves.
Projects Completed
Catherine Street Area Utility Infrastructure Upgrades | Completed November 2021. Financed by utilities reserves.
Central Power Plant 13,200 Volt Switchgear Upgrade | Completed October 2021. Financed by utilities reserves.
Central Power Plant Expansion | Completed January 2022. Financed by utilities reserves.
W.K. Kellogg Institute and Dental Building Expansion and Renovation | Completed June 2022. Financed by state capital appropriation, the Office of the Provost, the School of Dentistry and investment proceeds.
Detroit Observatory Classroom and Accessibility Addition | Completed July 2021. Financed by the Bentley Historical Library, gifts and investment proceeds.
Carl A. Gerstacker Building Herbert H. Dow Building Center for Ultrafast Optical Science Expansion | Completed November 2021. Financed by the College of Engineering.
Medical Campus Utility Infrastructure Upgrades | Completed November 2021. Financed by utilities reserves.
New Dance Building | Completed July 2021. Financed by investment proceeds, the School of Music, Theatre & Dance gifts and resources.
Central Campus Classroom Building and the Alexander G. Ruthven Building Renovation and Addition | Completed December 2021. Financed by investment proceeds.
University of Michigan Health System | Financed by the University of Michigan Health System.
- Brighton Center for Specialty Care Central System Replacement | Completed February 2022.